Overview
- The government detailed 3.4 billion pesos for transport across 10 municipalities, including Mexibús expansions and a new Ixtapaluca trolleybus now licited and adjudicated with the executive project in development.
- Conagua reported 2.6 billion pesos invested in 2025 and early 2026 across 101 potable water and drainage actions, within a 7.4 billion peso program slated to finish in 2028 for more than 6.4 million residents.
- The plan allocates 5.3 billion pesos to expand and build vehicular bridges, with 317 million exercised in 2025 as projects move into new construction phases this year.
- Six upper‑secondary schools were built in 2025 in municipalities including Chalco, Chimalhuacán, Ecatepec, Ixtapaluca, Nezahualcóyotl and Texcoco, with three more set to begin in 2026 in Chicoloapan, La Paz and Valle de Chalco.
- IMSS Bienestar said all hospitals and health centers in the zone have been intervened, citing 16 hospitals rehabilitated to date and a planned 1.6 billion peso investment in 2026 for additional hospital and clinic works.