Dubai Opens 700m Al Qudra Bridge to Cut Intersection Delays

RTA says the four‑lane span will sharply reduce waiting times, raise corridor capacity, with further ramps and bridges scheduled through Q4 2026.

Overview

  • The Roads and Transport Authority opened the 700‑metre, four‑lane bridge on Sunday, August 9, 2026, completing the main traffic layout at the Al Qudra intersection and cutting reported waiting times from about seven minutes to one.
  • RTA says the new span raises intersection capacity from roughly 7,800 vehicles per hour to about 19,400 vehicles per hour, allowing more traffic to flow without stopping at the junction.
  • The bridge sits on the southern side of the intersection and serves traffic heading toward Al Qudra City, joining the opposite bridge that opened in February to finish the junction’s primary configuration.
  • The wider Al Qudra Road Development Project covers an 11.6km upgrade that includes roughly four kilometres of bridge work, three kilometres of service roads beside Sheikh Zayed bin Hamdan Al Nahyan Street and lane additions on Emirates Road, and RTA expects corridor journey times to fall from about 9.4 minutes to 2.8 minutes when finished.
  • RTA plans more works through the rest of 2026 — a near‑term free‑flow ramp for traffic from Jebel Ali and two side‑ramp bridges in Q4 (a 500m link toward Jebel Ali and a 900m link toward Downtown/DXB) — which should let motorists change direction without disrupting main carriageways and improve access for roughly 400,000 residents in nearby communities.