Overview
- The transport hub will be closed from June 30 to July 21 for the replacement of a heavily worn track crossing.
- Eight of the city’s twelve tram lines will be affected and bus services will operate on alternate routes under the summer holiday schedule.
- The overhaul carries an estimated price tag of €1.9 million, with DVB seeking €1 million in federal and state funding.
- DVB has preassembled and tested the new track sections at its Reick depot to shorten installation time on site.
- Passengers can access detailed diversion maps and timetable updates via DVB’s website and information displays at stops.