Overview
- The central procurement office released tender documents, with offers due by 6 October and awards planned for December.
- Four planning offices are to be commissioned to develop parallel designs by the end of May 2026 for public discussion before a Stadtrat decision.
- City officials clarified that the previously cited €18 million covered only contractor work on spans A and B, with total demolition costs confirmed at €32 million.
- The cost breakdown includes about €21 million for spans A and B, roughly €6 million to remove the collapsed span C, and around €5 million for site safety, sensor-based assessments, and traffic changes.
- The Stadtrat has approved a four-lane replacement, with construction targeted to begin in the second quarter of 2028 and completion planned for 2031.