Overview
- The project is divided into two phases, with Kidani Village undergoing work from October 2025 to May 2026 and Jambo House from May 2026 to January 2027.
- General contractor Barton Malow filed the Notice of Commencement this week, signaling that all approvals are in place for the Kidani Village phase.
- Renovation will focus on hard goods upgrades, including a full replacement of fixtures, furniture and finishes in guest rooms.
- Guests can continue to enjoy pools, dining venues and recreational activities throughout the daytime construction.
- This overhaul aligns with Disney World’s broader phased strategy to modernize its resort accommodations.