Overview
- On Tuesday, August 11, CEO Evelyn Palla ordered a formal review to reprioritize the multi‑year Generalsanierungen program after delays and higher costs.
- The company plans to stop reopening whole lines at once and instead return sections to service step by step while running more conservative, staged tests and approvals for Leit‑ und Sicherungstechnik (signalling and safety systems).
- The shift responds to specific failures in execution, most visibly the protracted Hamburg–Berlin reopening, which still requires additional night works and temporary closures to finish signalling commissioning.
- Deutsche Bahn says the new approach will likely extend local passenger disruption on some routes in the short term but should deliver more reliable corridors over time.
- The program still targets more than 40 high‑traffic lines to 2036, resources will be refocused on highest‑impact projects, and freight operators remain critical because full closures force long detours; exact rescheduling has not yet been published.