Deutsche Bahn Flags About €16 Billion Cost for German Brenner Feeder

The transport ministry is sending DB’s plans and the regulator’s review to the Bundestag so parliament can pick the route that will unlock the tunnel’s capacity.

Overview

  • Deutsche Bahn disclosed Monday that planning and construction for the German feeder from Munich to the Austrian border are now estimated at €8.57 billion with roughly €7.6 billion set aside for risk and inflation, bringing the package close to €16 billion.
  • Project leader Johannes Neumaier said the inflation buffer was deliberately high—with provisions up to 10 percent—but added that DB intends to use risk management to avoid spending the full contingency.
  • The preferred German alignment would run about 64 kilometres with 39 kilometres tunneled because prolonged local opposition in Bavaria pushed the company toward deeper tunneling to limit surface impact.
  • The Federal Ministry of Transport will forward DB’s planning files, a ministerial report and the Federal Railway Authority’s assessment to the Bundestag, which must now decide the final German route and the project’s next legal steps.
  • The feeder is essential to use the Brenner Base Tunnel and to speed travel on the Scan‑Med corridor; Austria and Italy have progressed further on their links while Germany’s choice will shape costs, local disruption and whether service can match the tunnel’s planned operation from 2032.