Demolition Progresses on Berlin's A100 Ringbahn and Westend Bridges
Controlled dismantling of the aging structures continues with advanced safety measures, while plans for rapid replacement are underway.
- Demolition of the Ringbahn and Westend bridges on Berlin's A100 is proceeding as planned, with significant progress reported on both structures.
- Specialized equipment, including 'Knabberer' devices and engineered fallbeds, is being used to ensure controlled dismantling and protect nearby S-Bahn infrastructure.
- The Ringbahn bridge demolition, which began Saturday, is on track to be completed by Thursday, with debris processing and recycling ongoing.
- Approximately 12,400 tonnes of construction debris are being systematically crushed, sorted, and recycled to support sustainable urban renewal efforts.
- Public livestreams provide real-time updates on the demolition, while planning for rapid bridge replacement aims to minimize disruptions to S-Bahn operations.