Demolition of Structurally Unsound Wuhlheide Bridge Advances on Schedule

The Berlin bridge's closure has caused significant disruptions, with tram lines and footpaths expected to reopen next week as demolition progresses.

Image
Image

Overview

  • Demolition of the Wuhlheide bridge, deemed at risk of collapse, began on May 24 and is proceeding according to schedule.
  • Heavy equipment arrived overnight on Friday to Saturday, enabling daytime work over the weekend, though no nighttime operations are planned for weekends.
  • The bridge has been completely closed since the previous Monday, impacting traffic, tram services, cyclists, and pedestrians.
  • Disruptions to public transport and road traffic have been significant, with local authorities working to mitigate delays.
  • Pending progress, the tram line and footpaths beneath the bridge could reopen by next week, according to Verkehrsverwaltung and Senator Ute Bonde.