Delhi CM Orders ACB Probe Into Barapullah Phase-III Payout Irregularities

Rekha Gupta cites negligence in a court-mandated Rs 175 crore payout; the nearly complete project now awaits tree-removal clearance.

Overview

  • Rekha Gupta has directed the Anti-Corruption Branch to examine alleged irregularities in the Rs 175 crore court-mandated payment to the Phase-III contractor.
  • The probe will investigate possible complicity among PWD officials and why a contractor’s earlier Rs 35 crore settlement offer was ignored.
  • Delhi High Court ordered the Rs 175 crore payout in May 2023 after an arbitration tribunal awarded the contractor Rs 120 crore for delays and withheld dues.
  • The 6.2-kilometre corridor from Sarai Kale Khan to Mayur Vihar Phase-III is 87 percent complete but stalled pending environmental clearance for tree removal.
  • Gupta has warned that no further delays will be tolerated and assured sufficient budgetary support to finish the project this year.