Overview
- Crews carried out a continuous, shift-based demolition over the weekend and the Autobahn GmbH expects the A99 to reopen for commuter traffic at 05:00 on Monday, 23 November after final debris clearance.
- The 1973 bridge showed significant age-related damage and officials said it had to be taken down in one piece to prevent the remaining structure from collapsing onto the motorway.
- Contractor Mailhammer worked with up to eight excavators and about 50–60 people around the clock, removing roughly 2,500 cubic meters of concrete and separating material for transport.
- Traffic management included a full closure between Kreuz München-Süd and München Ost, advance warnings and diversions, and heavy use of a temporary Behelfsbrücke that has carried traffic since August with only localized congestion reported.
- Reconstruction will begin immediately with a planned replacement budgeted at about €30 million and scheduled for completion in autumn 2028, and officials say further long full closures are not expected during the rebuild.