Crete’s New Kastelli Airport Advances as Heraklion Strains Under Record Traffic

Officials still target a trial in August 2026 with opening likely in February 2027.

Overview

  • Government updates put construction at about 40% complete as of April 2025, with a Minoan-site discovery resolved by relocating the planned radar tower.
  • The replacement hub for Heraklion is designed to handle 10 million passengers at launch and later up to 18 million, featuring biometric checks, on-site green energy and new road links across the island.
  • Heraklion set a passenger record in 2024, with summer volumes reported at least 60% above the airport’s nominal capacity.