Overview
- Córdoba's City Council has approved a €549,356 tender for the pedestrianization of Avenida de la Viñuela, with construction set to begin in September 2025 and finish by March 2026.
- The Avenida de la Viñuela project will include a single-level platform, urban furniture, LED lighting, and the planting of magnolias, orange trees, and vegetation beds.
- Valencia's government will formalize a contract this week for the phased redesign of the Plaza del Ayuntamiento, simplifying the project to align with budget constraints.
- The initial step in Valencia's plan involves reconnecting central bus lines to improve public transport access to the city center.
- Valencia's phased construction approach could allow work on the Plaza del Ayuntamiento to begin as early as 2027, pending design completion and budget adherence.