Corte dei Conti Rejects Third Addendum to Messina Bridge Convention, Halting Next Step

Motivations will be published within 30 days as the ruling follows October’s refusal to clear the Cipess decision.

Overview

  • Italy’s audit court did not admit to the visto or registration the August 1, 2025 MIT–MEF decree approving the third addendum to the 2003 convention with Società Stretto di Messina.
  • The rejected addendum is tied to the August Cipess resolution on funding and approval of the executive project, which the Court also declined to clear at the end of October.
  • The non-admission blocks the decree’s registration, effectively preventing the program agreement required to advance the roughly €14 billion project.
  • The Court said its detailed reasoning is being drafted and will be issued by formal deliberation within thirty days.
  • Transport Minister Matteo Salvini called the outcome unsurprising and said experts are preparing clarifications, while opposition figures argued the government was pushing an illegitimate process.