Corrosion Forces Two-Year Delay in Oldenburg Station Hall Renovation

Inspections uncovered corrosion that pushed the completion date to late 2029, with Deutsche Bahn upholding its €80 million budget to safeguard the 1915 structure.

Gleishalle im Oldenburger Hauptbahnhof (Archivbild)
Image

Overview

  • Deutsche Bahn discovered severe corrosion on steel components during inspections at a Westoverledingen workshop, expanding the repair scope.
  • The renovation timeline has been shifted from the original end-2027 target to the end of 2029.
  • The project’s budget remains at approximately €80 million despite the extended schedule.
  • Work will proceed in phases, with the hall ship over platforms 5/6 set to finish by mid-2027 before sections over tracks 3/4 and 7/8 are tackled.
  • Passengers will face temporary restrictions and periodic platform closures at Oldenburg Hauptbahnhof throughout the renovation.