Controlled Demolition of Bad König’s B45-Talbrücke Set for Early August

Rail services are slated to resume by the end of the summer holidays following preparatory demolition work.

Image
Image
Image

Overview

  • Mid-May inspections uncovered concrete cracks that led to immediate closure of the B45-Talbrücke to road and rail traffic.
  • Preparatory demolition work is slated to begin by late June, including a temporary span over the Mümling and a ramp to facilitate debris removal.
  • A controlled explosion is scheduled for the first week of August to clear the existing structure for reconstruction.
  • Local businesses and commuters continue to contend with long detours and logistical challenges following the bridge shutdown.
  • Authorities are reviewing innovative construction and procurement methods for the replacement, while monitoring four similar Hessian bridges amid calls for further safety checks.