Overview
- An internal 75-page failure analysis commissioned by the contractor documents at least 85 distinct defects in the pool lining, including blisters, peeling and cracks that were photographed and cataloged in detail.
- The report blames the failures on improper materials and rushed work and cites specific technical problems such as improper mixing in application guns, spray mist landing on dried coating, and insufficient time for the coating to cure as required.
- The analysis says some peeling likely occurred because workers applied coating the day before the pool was refilled when the material required 72 hours to cure, which helps explain the algal bloom and blue flakes that appeared after the June refill.
- The contractor was awarded a no-bid $14.7 million contract and says it is completing warranty repairs; crews have returned and refilling of the basin has begun while federal oversight, preservation suits and liability questions continue.
- The findings conflict with earlier administration statements that blamed vandalism and cleared materials in tests, raising new questions about contractor selection, oversight of the work, and potential costs and timelines for a lasting repair.