- Consorcio EPiura formally terminated Contract No. 065-2025-GRP through a letter dated December 15, citing an inability to continue under state procurement rules.
- The Dirección General de Construcción scheduled a physical verification and inventory for December 19 and appointed a committee of engineers to carry it out.
- Work has been fully halted since early November, with executed progress around 1.64% versus a programmed 17–23% according to the Comptroller’s control report.
- Unanswered technical Queries No. 48 and 50 flagged serious structural risks in the existing stands, with specialists recommending complete demolition of all tribunes.
- A Regional Council special commission reported administrative, technical and transparency deficiencies affecting both the Miguel Grau remodel and the Campeones del 36 technical-file reformulation.