Overview
- OOAPAS announced the scheduled discharge concluded after operations executed during the weekend at the Cointzio reservoir in Morelia.
- Conagua reported the dam reached about 100.26% of capacity, prompting a controlled release of 5 m³/s between August 23 and 24.
- The action was authorized by the Comité Técnico de Operación de Obras Hidráulicas to reduce flood risk during the active rainy season.
- Authorities said most of the outflow was directed to the Río Grande and Lake Cuitzeo, with only minor level increases of roughly 5 centimeters expected.
- OOAPAS noted the release was through the service outlet rather than the gates, and agencies will continue monitoring and issue advance notices if additional actions are needed.