The utility will appoint a third-party panel to examine how seismic inputs for the Hamaoka review were prepared.

Overview

  • Chubu Electric disclosed on January 5 that part of the data it submitted for the Hamaoka Nuclear Power Plant’s conformity review was handled inappropriately.
  • The issue centers on how the plant’s design-basis ground motion, a key parameter for seismic design, was formulated.
  • Company statements and reporting indicate the methods used differed from what was described at Nuclear Regulation Authority review meetings.
  • Chubu said related figures tied to the ground-motion assessment were intentionally understated in reports to regulators.
  • The company said it will set up an independent committee to investigate the matter.