- The groundbreaking for Concourse E took place Tuesday, Nov. 17, 2026, and starts the $640 million first construction phase that city officials say will bring 14 gates into service by 2030.
- The full Concourse E is a $917 million, two‑phase build that will add 24 gates in total with a $277 million second phase planned to add 10 gates and open in 2034.
- Released renderings show a light-filled, hospitality-style concourse with wood finishes, interior greenery, skylights and a rooftop oculus called “The Halo,” plus an underground tunnel linking the new concourse to Concourse D.
- Concourse E is part of the $8.7 billion ORD Next program and is being financed through airport bonds repaid with landing fees and airline rents, with City and airline agreements expected to shape the pace of future work.
- City officials pitched the project as a jobs and competitiveness boost for Chicago while analysts warn the long, phased construction timeline could prolong congestion and operational strain during successive projects.