Overview
- CFE says 27.31% of its January–October 2025 generation came from clean sources.
- The utility repowered 23 of 166 hydro units, adding 89.2 MW and extending those units’ service life by about 50 years.
- At the Puerto Peñasco solar complex, 420 MW from Sequences I–II are in commercial operation, with Sequence III in contracting and Sequence IV in technical preparation.
- Intensive maintenance delivered 503 interventions, lifting offered capacity by 2,439 MW in May–July versus 2024 and cutting low reserve-margin days to one from 12.
- Net thermal efficiency rose from 34.39% to 35.44% year over year, and hydraulic reserves rank among the largest in 25 years, which the company says underpins summer 2026 reliability.