Particle.news

Download on the App Store

Centre Drafts Exemption From Environmental Clearance for Standalone Cement Grinding Units

The move could ease approval for Ambuja’s proposed Kalyan plant, with objections invited for 60 days.

Overview

  • The environment ministry’s September 26 draft would exempt standalone cement grinding units without captive power plants from prior environmental clearance.
  • It also proposes to drop mandatory public consultation and detailed EIA for these units, citing lower pollution potential.
  • The Expert Appraisal Committee endorsed the change, noting the absence of calcination and clinkerization and encouraging rail or electric-vehicle logistics.
  • An MPCB official said the draft is open for objections and suggestions for 60 days before a final decision is taken.
  • Ambuja Cement’s Rs 1,400 crore, 6 MMTPA Kalyan project at the former NRC site faces strong local opposition over air-quality concerns, even as the draft could ease its path.