Overview
- The program kicked off on August 18 with 50 specialized teams set to repair 10 km of main roads each night until its 1,000 km goal is met in December.
- A daytime response axis has deployed 50 additional crews to fix citizen-reported potholes within 48 hours via *0311 and the upcoming BacheTel WhatsApp chatbot.
- Contracts and preparatory bids are underway for an October 2025–May 2026 repaving phase that aims to resurface 250 km of the city’s 217 designated primary avenues.
- Officials will coordinate nightly road closures with the city’s security agency and release weekly intervention calendars through social media and official channels.
- The water management secretariat is addressing 37 sinkholes on primary roads and 116 on secondary streets, and is designing a 2 km drainage collector for Avenida de las Torres with a 50 million-peso budget.