Calgary Panel Cites Systemic Failures, Calls for 12–14‑Month Replacement of Failing Feeder Main

City leaders pledge to spare no expense to stabilize a strained water supply.

Overview

  • Mayor Jeromy Farkas warns the water supply is at a critical level and urges residents to cut daily use by 25 to 30 litres to maintain firefighting capacity.
  • Crews have installed a new pipe segment, completed welding, and begun backfilling as emergency repairs continue on the Bearspaw South feeder main.
  • An independent panel confirms years of deferred inspections in 2017, 2020 and 2022 despite longstanding concerns about the prestressed concrete pipe.
  • The panel deems the line in disrepair with further breaks likely and urges accelerating a steel replacement to be operational within 12 to 14 months, earlier than the current 2028 plan.
  • The report identifies overreliance on acoustic fibre‑optic monitoring that failed to flag the Dec. 30 rupture and recommends a dedicated water utility with independent oversight to strengthen accountability.