Overview
- The Union Cabinet approved the project on Wednesday to build a 900-metre, 18-metre-deep container terminal at Kamarajar Port with a total annual capacity of 2.0 million TEUs.
- The expansion will be delivered in two phases costing a PPP component of Rs 4,288.26 crore, split as Rs 2,429.32 crore for Phase I (1.1M TEU) and Rs 1,858.94 crore for Phase II (0.9M TEU).
- The terminal is designed to handle ultra-large mainline vessels up to 400 metres and about 24,346 TEUs and construction must be completed within 48 months of start.
- The project will be awarded by open global competitive bidding on a 40-year DBFOT concession where the selected private concessionaire will finance the PPP works and recover costs through user charges while Kamarajar Port will fund about Rs 450 crore of dredging.
- Officials say the scheme responds to near‑full use of the existing 0.8M TEU terminal, rising container volumes from the Chennai–Ennore industrial region, and national maritime goals such as Maritime India Vision 2030 that aim to strengthen the port as an East Coast gateway.