Buryatia to Replace Contractor on Ulan-Ude’s Third Uda Bridge, 2027 Deadline Stands

A Nov. 17 court hearing on termination precedes a new tender, with financing already in place.

Overview

  • Governor Alexey Tsydenov said the core span is built, with the rail underpass and final surfacing and infrastructure works still to be done.
  • Rosavtodor has retained the budget for completion, enabling a fresh competition after an assessment and re-estimation of the remaining scope.
  • The current general contractor, Khotkovsky Avtomost, missed deadlines and originally won the 2019 bid with a bank guarantee of about 1.5 billion rubles.
  • Total project costs exceed 7 billion rubles, and roughly 4.2 billion rubles have already been invested.
  • The four-lane, 202‑meter by 26‑meter bridge will connect the Oktyabrsky and Zheleznodorozhny districts, is designed for 18,000 vehicles per hour, and is expected to cut traffic by about 30%.