Overview
- A Bundestag paper cited by Politico sets initial office use for the end of Q1 2026 and a full handover in Q2 2026.
- A Bundestag spokesperson confirmed the new timeline to dpa following the Politico report.
- Project costs have climbed from an initial €190 million to about €420 million by the end of 2024, with additional expenses expected from the delay.
- Earlier setbacks were attributed to construction defects, notably a leaking floor slab.
- Commission chair Omid Nouripour called a fixed date overdue and said preparations to occupy the building start immediately.