Buckingham Palace Renovation Faces Unforeseen Challenges
Asbestos and structural damage contribute to cost increases in the £369m refurbishment project, according to a National Audit Office report.
- The renovation project, which began in 2017, has spent £239m of its £369m budget so far.
- Asbestos and structural damage have led to significant cost increases and delays.
- Despite challenges, the project remains within budget due to effective planning and management.
- The East Wing renovation was completed 78% over its estimated cost, while other projects came in under budget.
- The National Audit Office highlights important lessons for future heritage projects.