Overview
- Boston City Council voted 12-0 to approve Councilor Julia Mejia’s resolution seeking an updated cost estimate for the city’s share of the project.
- The mayor’s office reported $12 million spent on demolition and site work and $76 million designated to contractors, with final bid awards expected in early 2026.
- The last public estimate for the city’s share was $91 million after an initial $50 million projection, and an internal document showed a worst‑case scenario near $170–172 million that the mayor called disaster planning.
- The redevelopment is a public–private partnership with Boston Legacy FC, with the overall project expected to exceed $200 million and the team limited to 20 games and 20 practices annually under its lease.
- Opponents have appealed an April court ruling that rejected their lawsuit, and the city has denied public records requests for its internal cost projections.