Overview
- The Bombay High Court, which ruled Friday, refused interim relief to Pioneer Constructions and allowed the Sahakarnagar society to proceed with appointing a new developer.
- Justice Sandeep V Marne said residents’ need for safer homes outweighs the builder’s lost profits and warned that blocking the vote would prolong risk for tenants in 1957 buildings.
- The judge noted Pioneer had done virtually nothing on the project over 13 years and flagged that the firm withheld key facts, including its 2024 termination and a no‑objection certificate set aside in December 2025.
- Advocate Amrut Joshi was appointed as the sole arbitrator to hear payment and contract disputes, with the court stressing that any profit loss can be compensated later through an award.
- The stalled scheme spans 40,520 square metres of BMC land and covers 46 buildings with 826 flats plus shops and stalls, affecting about 900 tenants who have waited years for safer, larger homes.