Overview
- The real-time dashboard lists road-by-road status with ward and zone views, maps, search by road name, contractor and engineer details, and estimated timelines.
- Work paused for the monsoon will resume on October 1 with an initial push to finish partially completed roads before taking up new stretches.
- The Rs17,000-crore programme covers 2,121 roads totaling 698.73 km across the city.
- Official data shows 771 roads (186 km) completed, 574 roads (156.74 km) partially done, and 776 yet to start, placing overall progress at about half.
- Phase I is targeted for completion by May 2026 and Phase II in the first half of 2027, with about 25 roads dropped from the plan after citizen inputs or site constraints, some to be repaired in asphalt.