Overview
- Priority will go to 574 partially completed stretches totaling about 156.74 km, with additional work to begin on 776 roads where concreting has not started.
- The dashboard provides road-by-road status with contractor and engineer names, timelines, map search, and contact numbers for responsible engineers.
- The programme covers 2,121 roads spanning 698.73 km and is valued at about Rs 17,000 crore, with 771 roads finished and work pending on 776.
- BMC targets Phase I completion by May 2026 and expects Phase II to be executed to completion by the first half of 2027, according to officials.
- IIT Bombay remains the independent third‑party quality monitor, and at least 25 roads have been dropped from the plan or shifted to asphalt after citizen feedback and site constraints.