BMC Pushes November Finish for BandraDharavi Phase‑1, Sets 18‑Month Timeline for Full Project

Officials tightened oversight by requiring advance traffic NOCs.

Overview

  • Phase‑1 of the BandraDharavi flyover rebuild is about 90% complete with a November 30 target, following a site inspection by Additional Municipal Commissioner Abhijeet Bangar.
  • After Phase‑1, the southern lanes of the existing bridge will open to provide direct access toward Mahim Causeway to ease traffic flow.
  • Work orders for Phase‑2 will be issued shortly, with the entire reconstruction slated to finish within 18 months, according to the BMC.
  • The E. Moses Road–Dr. Annie Besant Road nullah bridge in Worli stands at roughly 30% completion with a December 2026 deadline to create a new east‑west link and decongest Worli Naka, Mahalaxmi and Lower Parel.
  • The Bandra Railway Station–MHADA skywalk is about 80% complete and is targeted to open by December 31 in line with Bombay High Court directions, with contractors warned of action for any delays.