BMC Installs 12 Girders, Fast-Tracks Bellasis Flyover to December 2025

Western Railway handles work within tracks, with BMC advancing approach roads ahead of girder bracing and slab casting due by mid-September

Overview

  • The civic body advanced the opening date by four months, targeting December 31, 2025 instead of April 2026.
  • The project team completed the installation of twelve 36-metre girders on August 11, marking a major technical breakthrough.
  • Girder bracing, deck sheet installation and slab casting are slated for completion by September 14, requiring around forty traffic and power blocks.
  • Western Railway is executing structural work within railway limits while the BMC builds the approach roads under a clear division of responsibilities.
  • The Rs 110-crore project is funded with Rs 70 crore from the civic authority and an expected Rs 40 crore contribution from the railways, alongside a MahaRail agreement for nearby cable-stayed infrastructure.