Bihar Suspends Two Engineers, Moves to Blacklist Contractor After Rohtas Ropeway Trial Collapse

Officials blame weak supervision during a Dec. 26 load test, with IIT Patna now auditing the design.

Overview

  • The ropeway suffered a failure during a load trial when a wire rope slipped, damaging a tower and four trolleys, with no injuries reported.
  • A high-level committee led by the BRPNNL managing director was constituted to probe the incident and asked to submit a report within 24 hours.
  • The government has initiated suspension proceedings against the project and junior engineers of BRPNNL and begun the process to blacklist the contractor, RRPL.
  • IIT Patna experts are conducting a design audit and examining material quality, while rectification is to proceed under contract terms.
  • The 1.32-km project, costing about Rs 13–13.65 crore to connect Rohtas block with Rohtasgarh Fort and Rohiteshwar Dham, has faced years of delay, as locals had earlier alleged substandard materials and shallow foundations.