Overview
- The phase one budget has increased to between US$7 billion and US$7.4 billion, representing roughly a 30 per cent overrun against the original US$5.7 billion estimate.
- First production is now slated for mid-2027, marking a six-month delay from the initial end-2026 target.
- BHP attributes the cost increase and schedule delay to inflationary pressures, evolving design scope and lower-than-expected construction productivity.
- As of mid-2025, phase one is 68 per cent complete following US$4.5 billion in spending, with US$400 million already invested toward phase two.
- The company is considering deferring phase two by two years into its fiscal 2031 cycle to align with projected potash supply growth.