Berlin’s A100 Resurfacing Starts Sunday, Bringing Staged Exit Closures Toward Wedding

Lane reductions before the Britzer Tunnel aim to keep traffic flowing inside.

Overview

  • The VIZ confirms resurfacing on the A100 toward Wedding from 12 October to 8 November with a three‑phase schedule.
  • Phase 1 runs 13–19 October with the right lane closed and the Gradestraße and Oberlandstraße exits shut from Sunday at 2 a.m.
  • Phase 2 spans 20 October–2 November with all four exits closed, traffic reduced to a single lane, and detours via Kreuz Schöneberg and Sachsendamm.
  • Phase 3 lasts 3–8 November with Tempelhofer Damm remaining closed and the Alboinstraße exit restricted for outbound traffic.
  • Short full closures include 12 October from Dreieck Neukölln to Tempelhofer Damm with a diversion via Buschkrugallee, plus 19 October and 2 November A113 diversions at Späthstraße, while the Treptow direction stays open and authorities urge drivers to avoid the corridor or use public transport.