Berlin cuts planning times to speed up bridge replacements

City legislators approved a five-year pilot reducing bureaucratic steps to restore compromised crossings faster

Image
Image

Overview

  • Traffic Senator Ute Bonde’s administration will merge two preliminary planning reviews into a single approval to streamline early-stage project clearance.
  • The formal review period for bridge planning documents is set to shrink from nine months to one month under the new rules.
  • Exemption from certain state budget execution regulations is projected to shorten total project schedules by one to two years.
  • The Hauptausschuss des Abgeordnetenhauses endorsed a five-year trial of the accelerated procedures this week.
  • Continuous planning and specialized construction methods are expected to deliver an extra three to six months of time savings on replacement projects.