Berlin Court Approves Jahnstadion Demolition After Revised Wildlife Protections
The decision overturns a previous halt on the project following additional measures to safeguard sparrow habitats.
- The Berlin Administrative Court has ruled to allow the continuation of demolition work at Jahnstadion, reversing a prior decision from November 2024.
- The earlier halt was implemented due to concerns over the loss of sparrow nesting sites, which were deemed insufficiently mitigated by initial plans.
- The court's reversal follows new measures by the Berlin Senate, including the installation of five permanent sparrow nesting boxes and monitoring to ensure their use.
- The Jahnstadion demolition is part of a €200 million project to create an inclusive sports facility, which has faced significant opposition from local groups.
- A citizens' initiative opposing the project has garnered over 14,000 signatures, citing concerns over financial and environmental sustainability.