Berlin Awards A100 Ringbahn Bridge Rebuild to Habau/MCE, Opening Targeted for Summer 2027

Officials are fast‑tracking the project through a bonus‑malus contract using prefabricated steel elements.

Image
Image
Image

Overview

  • Construction is slated to begin in the second half of October after preparatory work, with a build time of under two years.
  • The federal government will finance roughly €80 million in costs for the replacement project.
  • The design switches from prestressed concrete to a steel substructure with factory‑assembled components to shorten on‑site work.
  • The Westendbrücke, also demolished, will be rebuilt largely in parallel as authorities aim to reopen the A100 northbound between Messedamm and Spandauer Damm in summer 2027.
  • Traffic and rail operations are being coordinated with Deutsche Bahn, with S‑Bahn closure windows still under negotiation, and added noise barriers plus low‑noise asphalt promised for nearby residents.