Overview
- Trial runs extended from depot to stations on Tuesday and continued into Wednesday, with trains running from Byappanahalli through KR Puram to Doddanekkundi as BMRCL advances testing.
- BMRCL has been progressively charging 33kV traction cables and the third rail and expects kinematic mainline tests in November before full signalling integration is completed.
- Signalling integration remains the key technical hurdle and about 2 km of track and station work plus mandatory safety inspections must finish before commercial services start.
- Prime Minister Narendra Modi will inaugurate the 7.5 km elevated Pink Line section on November 13 and passenger services will begin at 6 a.m. on November 14 with five trains running at roughly eight-minute intervals.
- A sharp funding dispute has erupted over accounting for Centre‑guaranteed foreign loans, with Karnataka saying the State bears about 84% of combined metro costs and BJP figures arguing the Centre covers roughly 53–54%, a clash that will shape appeals for more central support.