Overview
- The club opened 23,000 seats in the Tribuna and Gol Sur for the November 7 session, and the available tickets sold out.
- FC Barcelona designated the Phase 1A gathering as a technical trial to validate access, systems and stadium operations.
- Official matches at Spotify Camp Nou remain on hold because the Phase 1B first-occupancy license has not yet been granted.
- The redevelopment began in late 2022, fully closed the venue on June 1, and has cost about €1.45 billion to date.
- The project targets a final capacity of around 105,000 and adds features such as a Mossos d'Esquadra post, a centralized network of more than 700 cameras and faster evacuation routes.