- The Ministerio de Transportes reports that 80% of the T1 rail access works are complete and on schedule for December delivery.
- Two recent contracts worth a combined €4.4 million cover main and support electrical feeds essential for powering the new line.
- Underground stations at terminals T1 and T2 now have tracks, platforms, electrification, climate control and passenger access facilities in place.
- Alstom’s first of ten shuttle trains ordered by FGC is in advanced production with summer testing planned for the prototype.
- Operated by FGC under the name R-Aeroport, the shuttle will link the airport to Sants station in about 19 minutes and serve an estimated 7 to 9 million travelers annually.