Barapullah Phase-III Congestion Persists as PWD Rolls Out Immediate Fixes

Short-term lane channelisation, a proposed U-turn and consultant reviews are being used to restore traffic flow and determine responsibility for the Rs 1,635 crore corridor.

Overview

  • Since its opening last month, the newly opened Barapullah Phase-III stretch has seen persistent crawling traffic and long queues that triggered a formal advisory from the Delhi Traffic Police.
  • Engineers point to traffic-geometry problems where a three-lane flyover narrows into a two-lane existing road near Sundial Park and multiple large approaches converge, forcing repeated merges that create stop-start waves.
  • The PWD has begun short-term measures such as lane channelisation and better lane use, proposed a dedicated U-turn near the Gurdwara to separate local traffic, and is weighing road-widening at key merge points.
  • Officials say they will appoint traffic and structural design consultants, coordinate with Google Maps to update routing data (which the PWD says can take about 15 days), and pursue longer-term structural fixes.
  • The issue has become political with PWD minister Parvesh Verma blaming the previous AAP government for planning decisions, AAP demanding a CBI probe into sanctioning, and the PWD filing police complaints over videos showing deliberate road damage.