Baja California Unveils Privately Financed Elevated Morelos–Otay Expressway

The plan relies on toll revenue under a 30-year concession.

Overview

  • The state announced the 12-kilometer Sube‑T elevated road linking Morelos to the Otay border crossing, pitched to cut trips from about 45 to 15 minutes.
  • Designs call for more than six lanes with a continuous flow layout, 12 entrances, 11 exits, and a preferential bus lane with 15 stations.
  • Project leaders said the investment tops 20 billion pesos and will be funded entirely by private capital at the investors’ risk.
  • Users would pay variable tolls that adjust by time, day, and distance, with a working range of about 8 to 11 pesos per kilometer.
  • The state granted a 30-year operating concession to a new firm, Supervía Bajacaliforniana, and named Idinsa and Prodemex to build the route in about 33 months.