Overview
- Sedena’s military engineers will execute the teardown and rebuild on Prolongación Corregidora Norte as part of the federal Tren México–Querétaro project.
- Two lanes will close at El Cerrito/Tepetate, leaving one lane in each direction for several months, with duration estimates ranging from about four to eight months.
- AMEQ says more than 80,000 Qrobús users on 22 routes that use the corridor will face temporary detours and service adjustments.
- State mobility officials and the municipality will present a mitigation strategy and public information campaign on January 20 to manage traffic and transit impacts.
- Governor Mauricio Kuri and Mayor Felipe Macías report insufficient scheduling details from federal infrastructure authorities, while local reporting indicates Bernardo Quintana works would follow after Corregidora Norte.