Argentina Approves RIGI Incentives for La Rinconada Wind Park

The decision grants customs, tax and foreign‑exchange breaks that are conditional on tight investment deadlines and allows the 94.5 MW project to supply renewable power to Tenaris’s Siderca plant under priority dispatch.

Overview

  • The Ministry of Economy formalized Parque Eólico La Rinconada’s entry into the Régimen de Incentivo para Grandes Inversiones by publishing Resolución 1983/2026 on Monday, November 16, 2026.
  • Vientos La Rinconada will build a 94.5 MW park near Olavarría with a total investment of USD 230.754.206 and recorded its formal adhesion on October 23, 2026.
  • The resolution requires the company to complete the minimum computable investment by March 31, 2027 and to demonstrate at least 40% of that minimum within two years of notification to retain benefits.
  • Under RIGI the project may import capital goods with customs relief and access tax and FX incentives, CAMMESA granted 91.5 MW of priority dispatch, and the park will connect to the grid via TRANSBA’s new La China transformer station.
  • Tenaris presents the park as part of a wider renewables push that it says will cut emissions intensity and avoid about 100,000 tonnes of CO2 a year, while coverage differs on construction roles with some outlets naming Techint Ingeniería y Construcción and others attributing works to Tenaris.