Ardmore’s Piazza Redevelopment to Break Ground After Thanksgiving

Community input under cost pressure steered the design toward smaller retail with set-aside public parking.

Overview

  • Developers plan to start construction after Thanksgiving 2025, with work expected to take about two years and finish by fall 2027, according to township officials.
  • The five-story project will bring 270 apartments, nearly 30,000 square feet of retail, and about 480 parking spaces along Lancaster Avenue between Ardmore and Greenfield Avenues.
  • Plans were approved in 2021 and are exempt from Lower Merion’s 2019 three-story height limit because the application predated the ordinance.
  • A previously envisioned grocery store was dropped because it would have required two underground parking levels that became financially infeasible as interest rates rose; smaller dining options are now expected.
  • Negotiations produced over 100 public parking spaces, rear-site traffic routing, new pedestrian crossings, and an extension of West Athens Avenue to improve connectivity near Haverford College.