The company has sought temporary creditor protection to prepare an appeal against a ruling that it says undermined client confidence.

Overview

  • The group filed a notice of intention to appoint administrators after a sequence of legal and financial setbacks that left cashflow under strain.
  • Ardmore applied for a company moratorium on June 11 to gain short-term protection from creditors while it prepares an appeal against the High Court Building Liability Order.
  • Work has been paused on nine London projects, including the £500 million Tribeca mixed‑use scheme in King’s Cross, and multiple sites have reported stoppages and missed payments to staff and subcontractors.
  • The BLO came after Crest Nicholson won nearly £15 million for remediation at the Admiralty Quarter in Portsmouth and Ardmore says the judgment reduced client confidence and affected certified values on live contracts.
  • The collapse follows a year of losses and earlier restructuring, with Companies House filings showing a pre-tax loss of about £42.6 million to September 2024 and wider industry pressure from post‑Grenfell remediation claims.